Work Orders
14 total
Dispatched
7
On Site
3
Verified (90d)
4
Spend (Actual)
$112.8K
MCS-impacting only
| Asset | Site · ISP | Defect | State | Actual | Weather |
|---|---|---|---|---|---|
| T-19 | Mesa Verde Wind Aerones | leading edge erosion cat3 | dispatched | est $78,000 | — |
| T-31 | Mesa Verde Wind Aerones | blade root corrosion | dispatched | est $78,000 | — |
| T-50 | Mesa Verde Wind Aerones | coating breakdown | dispatched | est $78,000 | +1d |
| T-51 | Mesa Verde Wind Aerones | drivetrain major alarm | verified | $76,077 | +1d |
| T-62 | Mesa Verde Wind Aerones | leading edge erosion cat3 | dispatched | est $78,000 | +2d |
| T-64 | Mesa Verde Wind TAKKION | string underperformance | verified | $12,093 | +2d |
| T-71 | Mesa Verde Wind RNWBL | exposed fibres | on site | est $220,000 | — |
| T-12 | Lone Coyote Ridge TAKKION | string underperformance | dispatched | est $12,500 | +2d |
| T-28 | Lone Coyote Ridge TAKKION | minor lee | dispatched | est $12,500 | +2d |
| T-39 | Lone Coyote Ridge RNWBL | bonding failure | dispatched | est $380,000 | +1d |
| T-59 | Lone Coyote Ridge TAKKION | minor lee | verified | $12,249 | — |
| T-09 | Northstar Plains Aerones | blade root corrosion | on site | est $78,000 | +1d |
| INV-03-S21 | Big Bluestem Solar TAKKION | string underperformance | on site | est $12,500 | +2d |
| INV-06-S09 | Big Bluestem Solar TAKKION | coating wear | verified | $12,332 | +2d |